International Business Review 10 (2001) 305–322 www.elsevier.com/locate/ibusrev Managing inter-firm industrial projects — on pacing and matching hierarchies J. Dahlgren , J. Söderlund * School of Management, Linköping University, SE-58183 Linköping, Sweden Abstract The purpose of this article is to present a conceptual framework useful for understanding and analyzing the management and organization of the execution phase of inter-firm industrial projects. On the basis of an exploratory case study of a project within the ABB (Asea Brown Boveri) Group, we develop two concepts. One is pacing, which focuses on the mutual coordination of activities between client and contractor. Pacing refers to the temporal orientation of the parties involved in inter-firm projects. The other concept is matching hierarchies, which focuses on how the interacting parties establish joint-decision making in order to handle overall project-related dependencies and conflicts. The suggested concepts are linked to each other in the sense that a configuration with matching hierarchies provides the arena for solving pacing problems, while, on the other hand, the pacing process provides the mechanism for linking hierarchies. 2001 Published by Elsevier Science Ltd. Keywords: Project management; Project marketing; Client–contractor relationships; Temporary organizing; Coordination; Cooperation; Pacing; Matching hierarchies; ABB 1. In the midst of the storm “What is happening?” The project manager of one of ABB’s (Asea Brown Boveri) most important industrial projects could not believe what he was experiencing. In the last 11 months, some 10,000 letters, all full of questions and demands for new and renewed tests, had flooded the entire company. In the previous project in Finland * Corresponding author. Tel.: +46-13-284065; fax: +46-13-281873. E-mail address: jonso@eki.liu.se (J. Söderlund). 0969-5931/01/$ - see front matter 2001 Published by Elsevier Science Ltd. PII: S 0 9 6 9 - 5 9 3 1 ( 0 1 ) 0 0 0 1 8 - X 306 J. Dahlgren, J. Söderlund / International Business Review 10 (2001) 305–322 that he had been in charge of, only 75 letters were received during the entire project! 10,000 letters meant roughly 50 per day! And as if the sheer number of letters was not enough, the tone of the letters, seemingly insinuating lack of competence and expressing distrust, irritated those who were targeted. It’s impossible to work with a client who engages almost everyone in the organization with his questions. We don’t get the time to plan and think ahead when all of our time is consumed by reacting to the client’s requests. And I haven’t got the faintest idea what we should do to stop this. The above text is a short excerpt from our material on a project carried out by the Swiss–Swedish firm ABB. In the end, the project was a failure in terms of two of the normal success criteria for projects, on budget and on time, although the overdraft in time was caused mainly by factors external to the project. The client was satisfied with the functionality of the plant, but realized that the project could have been carried out with less resources devoted to negotiations and conflict resolution. The fact that the project was unsuccessful is in itself a reason for further analysis. Apart from this, we believe that two questions provide additional reasons for analysis: 1. What caused the behavior of the contractor and the client to differ so dramatically in intensity? 2. Why were the companies’ attempts to manage the relationship unsuccessful? In this paper we are going to suggest answers to these questions — answers that we believe will have some important theoretical implications. 2. Managing the violation of the decoupling principle In industrial inter-firm projects, combining the effort of several companies is of major concern. In such multi-organizational contexts, interdependencies in areas such as planning operations and information create uncertainty, which has to be resolved through the cooperation between the contracting parties. The need for coordination is thus a function of the degree of interdependence (Chisholm, 1989). In his discussion on project administration in the North Sea, Stinchcombe (1985, p. 70) particularly emphasizes the importance of the ‘decoupling principle’. The principle asserts that if two activities are highly interdependent, they should be carried out by the same organization, under the same authority. If this is not possible, the activities should be made independent (decoupled). In large engineering projects, where joint effort from several organizations is involved, interdependent engineering work is, however, often split up between organizations. This results in a violation of the decoupling principle. The reason is that an organization has to manage many interdependencies and the interdependence in engineering work is only one of them. Coup- J. Dahlgren, J. Söderlund / International Business Review 10 (2001) 305–322 307 ling in other areas, e.g. strategy and knowledge bases, must sometimes be given priority. Thus, what is important is not how to avoid violating the decoupling principle, but rather to increase our understanding of how to manage situations where it has to be violated. Cooperative strategies are often tied to the existence of real potential for future transactions (Macneil, 1980; Axelrod, 1984). Continuing relationships are generally considered a source of trust, stemming both from historical interactions and/or from expectations of future transactions (Bryman, Bresnen, Beardsworth, Ford, & Keil, 1987; Goodman & Goodman, 1976). In situations where contractors with turnkey responsibility use the same sub-contractors for repetitive projects a kind of quasifirm configuration emerges (Eccles, 1981). In these cases institutionalized behavior manifests itself in standardized interaction sequences supported by common experience, a common knowledge base, common interests and routines that lead to reduced uncertainty. The institutionalization of such relationships makes an organization adjust its culture, methods and practices to the other party. The institutionalization in turn reduces uncertainty and has the potential to trigger action (Sahlin-Andersson, 1992). A typical characteristic of project industries is the frequent lack of a continuing relationship between the main actors, which complicates attempts to coordinate interdependent activities (Bonaccorsi, Pammolli, & Tani, 1996; Cova, Mazet, & Salle, 1996; Kolltveit & Reve, 1998). In this respect a project might be viewed as a ‘one-night stand’ (Kavanagh, 1998; Meyerson, Weick, & Kramer, 1996). Even in a project involving a product or system with a long service life, e.g. a power plant, the client does not build strong, long-term relationships with the contractor. Although such an investment has a service life of more than 30 years, the client must be capable to manage it independently after the take-over. During the execution phase a mutual and tight relationship must be established because of the interdependencies and the uncertainty involved. This might not only lead to an intense work in bringing the organizations together, but also to activities in order to curb opportunistic behavior on the part of either party. Owing to the lack of expectation of future transactions, it might be assumed that this need for coordination leads to a reliance on formal mechanisms, such as contracts. Even though a contractual framework forms an important structural background to processes of interaction, it can sometimes also be an obstruction to control (Bresnen, 1990; Stinchcombe, 1985). The argument here is that projects are often carried out in environments and situations of high complexity and uncertainty, which call for organic structural characteristics (Chisholm, 1989; Söderlund & Andersson, 1998). Macaulay (1963, p. 61) found that some business people object to elaborate contracts because they indicate a lack of trust and blunts the demands for friendship, turning a cooperative venture into ‘an antagonistic horsetrade’. Hence, legal ordering is applied only when private ordering fails. 3. In search of a framework Academic work on the marketing and management of projects is definitely on the increase (Günter & Bonaccorsi, 1996; Lundin & Midler, 1998). Several attempts have 308 J. Dahlgren, J. Söderlund / International Business Review 10 (2001) 305–322 been made by researchers to expand our knowledge about client–contractor relationships in project-based industries. A significant trait in these attempts is that the execution phase has nearly always been neglected. Either studies on the interaction between the client and the contractor have focused on the time period prior to signing the contract (Bansard, Cova, & Salle, 1993; Cova & Holstius, 1993; Cova, Mazet, & Salle, 1993), or the focus has been on the period between projects (Hadjikhani, 1996). Both these strands of research have contributed greatly to the knowledge about projects, the marketing activities and the strategies for establishing and maintaining customer relationships. However, the literature dealing with the cooperation and coordination between the client and the contractor during the execution phase still suffers from meager attention and lack of good empirical research. The purpose of the present article is to present a conceptual framework for understanding and analyzing the management and organization of the execution phase of inter-firm industrial projects. Management is seen here, Sayles and Chandler (1971) suggest, as a form of handling organizational processes and rates of time. Our explorative case study indicates that the differences in rates of time were a major source of problems. Our study also points to hierarchy as an important feature of inter-firm projects. The mirroring and matching of the two firms’ respective hierarchies can thus be regarded as a way to handle the problems arising from the violation of the decoupling principle. 4. Methodology The study was initiated in January 1995 when we met with the top management of one of ABB’s subsidiaries to discuss the possible cases for describing and analyzing client–contractor relationships in industrial projects. We were looking for international projects that had caused the firm some problems and which were interesting from several perspectives and levels of analysis in the hope that the case would generate good descriptions of ‘typical’ project management problems. After discussing different types of projects we decided to make a pre-study of the project accounted for in the present paper. We soon realized that this project had several interesting aspects, both on practical and theoretical levels. The pre-study consisted of a day of discussion with the former project manager and one of the site managers, in order to get an overall picture of the project. They described the project, its scope, objectives, and major problems, and how the project finally had been executed and finalized a couple of months before we commenced our study. Our main study was divided into four intervals to make it possible for us to reflect upon the interviews and also to sum up and transcribe the interviews, and after that make a decision about the future direction of the study. On every visit to the company we met with the project manager to perform follow-up interviews. Every visit lasted for two days, during which we conducted interviews for approximately 6 h per day. At every interview we used a tape recorder. In total, our study required more than 20 interviews lasting between 1 and 5 h. Apart from the interviews, we had access to the written material about the project and several reports and messages from the client. J. Dahlgren, J. Söderlund / International Business Review 10 (2001) 305–322 309 From a methodological point of view, we believe that the best way to develop concepts and generate theory based on deep understanding is to use a single case study approach (Dyer & Wilkins, 1991). We rely on one in-depth study to provide a rich description for revealing the structure and context of social behavior observed in the focal project. The dialogue between theory and empirical observations is here of utmost importance for the construction of theory that is both empirically grounded and theoretically reflexive (Dyer & Wilkins, 1991, p. 616). On the basis of insights about context and underlying dynamics of the case (Easton, 1998), we develop a conceptual framework for future analysis of client–contractor interactions in projects similar to the one being analyzed in this article. At this stage we believe that it is more important to get a rich description of one case than to compare different projects. We suggest that a comparative approach might be an appropriate next step in this research effort (Eisenhardt, 1989). 5. The case ABB is one of the largest companies in the world. One of its business areas is power transmission. On average, a power plant is an investment of about 500 MUSD. The market is concentrated and competitive, consisting of three major competitors on the supply side and mostly state-owned enterprises throughout the world on the client side. The number of projects in this market is limited, and hence every single project is considered to be important. In 1965, ABB delivered the original plant to National Electric (code name). In the mid-1980s, ABB received indications that National Electric was planning to upgrade the existing plant and by 1988 ABB learnt that National Electric had carried out tests in cooperation with one of the major competitors of ABB. Shortly later, ABB sent a delegation to National Electric to get information and discuss plans for the upgrade. It turned out that some technical features of the project, e.g. the seismic conditions, the layout of the sites and the required noise reduction, were very complicated. 5.1. A project in the pipeline National Electric had several options for configuring the project. In what was seen as a bold step, a model based on the use of internal resources from National Electric together with additional individuals and companies was adopted as it appeared to be the most cost-effective, the most controllable and as an alternative which would most likely generate long-term benefits for National Electric. It promised to avoid the disadvantages of the other alternatives, which included: (i) lack of technical and quality control of a turnkey project; (ii) perceived high cost of project management organizations and their previous limited success in managing industrial relations in the country; and (iii) the need to avoid compromising National Electric’s long-term obligations. National Electric decided to divide the overall project into eight separate sub-projects, which were to be managed as either stand-alone, fixed-price contracts or small sets of fixed-price contracts. 310 J. Dahlgren, J. Söderlund / International Business Review 10 (2001) 305–322 As the project was crucial to National Electric, several experienced consulting firms (both technical consulting firms and administrative support) were contracted. Nothing was to go wrong. 5.2. The tender phase ABB was invited to take part in the tender process and initially a temporary task group headed by the sales manager was organized. A proper project manager was appointed as late as in the final discussions with the customer. The project manager explained it in the following words: The reason why I entered the project so late was because I was in the middle of finalizing another project. However, I was able to hand over that responsibility to others mainly because only details remained in that project. I discussed the new project with our CEO and he asked if I was interested in being project manager. I had about ten days to read through all the material and documentation about the project before we flew to National Electric to discuss the final parts of our bid. It was a stressful situation. It soon became obvious that an unusual amount of effort had to be put into answering questions from client’s representatives. One member of the project management team described the situation in these terms: It is rare that the customer drives the negotiations like this. They wanted to know and cover everything. They got into details and covered them thoroughly. They were so detail-oriented that it looked like they were trying to avoid all the risks in the project, no matter how minor. They wanted to make sure that nothing went unnoticed. Their technical director had a lot of questions during the final negotiations. It seemed like we were writing formal letters to deal with each question before the contract was even signed. We had expected to address most of these issues after the contract was signed (Project Manager). At this stage National Electric’s involvement was, however, taken as a positive sign. Although it generated a lot of extra work in the early phases, it might exclude some problems later on. Prior to the final bid, representatives of ABB flew out to meet the representatives of National Electric to discuss and clarify certain aspects of the project. The day after the ABB representatives had come back to Sweden, the sales department got the word — the customer wanted to enter into final negotiations with ABB. The sales manager and the project manager were back on a plane to the customer. The final discussions on price and details took only one day, and the contract was signed. In the J. Dahlgren, J. Söderlund / International Business Review 10 (2001) 305–322 311 meantime, the would-be project manager was interviewed by people from National Electric who accepted him as their counterpart. 5.3. Project start-up The ABB project organization slowly began to take form. The contract stipulated, among other things, that there should be a resident manager locally, whose task was, so to say, to smoothen out the operations and handle day-to-day communication. One of the project manager’s concerns was to find the right people: What worried me most was getting a technical director. My problem was that everyone I wanted was working in another project. But when the ABB management told me that I was free to recommend anyone, I did. I had worked with a very professional engineer in the past and knew he understood the project and its issues. He was ready for a new challenge. He particularly appreciated the fact that he would be responsible for commissioning the new plant (Project Manager). Much to the surprise of ABB, National Electric retained some of the consultants. Most importantly, their project manager was a consultant. ABB experienced the effects of the high involvement of consultants in National Electric too soon: We were worried from the first day. They came in with a lot of questions about details that clients normally don’t get involved with. They were asking detailed questions about implementation while we were still trying to put together an organization here at home. We didn’t even know what team we would have on site, and we were already trying to handle detailed client questions. The questions went much further into ABB’s organization than what normally was the case. We were busy trying to understand all of the aspects of the business we had agreed to perform. It takes a while to get ready for implementation in a project like this. We had to read and re-read the contract and the specifications to truly understand the scope of the technical solution and some of the technical problems (Technical Director). The high involvement of consultants had other consequences as well: They wanted both braces and belts. A consultant can’t give, he can only take, and he must have documents to be able to show what he has done and why he has done it (Technical Director). During the build-up phase of the ABB project organization, there was no real time for handling the client’s questions and proposals. ABB was therefore forced to react to client’s proposals rather than being able to actively formulate the rules of the game: We built our project organization far too late and far too slowly. I was alone but they had their organization running at full speed. (Technical Director) 312 J. Dahlgren, J. Söderlund / International Business Review 10 (2001) 305–322 I think that we failed in controlling the project. Everything had already been decided on when we entered the project. We have to make our moves early in order to be able to affect the rules of the game (Sales Manager). Ten months after the project had started, the project manager and the technical director of ABB met with the technical director of National Electric. The project manager of ABB knew he had problems when he learned that the client did not want to approve the ‘equipment specifications’, something that ABB needed in order to purchase equipment. The client also demanded more extensive tests than ABB’s time schedule and budget permitted. The project manager thought that they were losing control over the situation and that the relationship with the client was deteriorating. He realized that the project could not be managed properly if he constantly had to follow all of client’s directives. At this point, the project manager decided to call in his CEO in order to explain these concerns to the client. Our CEO had been around for a long time and knew how to handle these kinds of issues. I called him in because of that experience. Our CEO explained to their technical director exactly what would happen. If the client kept pushing us with detailed questions, the project would be delayed. Our CEO raised his voice a few times in the discussion. They finally agreed to ABB’s approach, but made a note that the sound levels might not meet the requirements of the specifications. The project manager felt he had taken a drastic measure: I would normally never move a project to that level of the organization. I would much rather take care of the problems myself, but I saw the project deteriorating and his intervention as the only way out. I think it was the only move that could be made. The project manager was not the only one who was frustrated with the client. The technical director of ABB had his share of concerns as well. They flooded us with letters. Each person involved in a minor facet of the project would have to answer, and each person would answer from his or her perspective. The client felt like they were getting conflicting information. Minor questions were driving an enormous amount of work. Whole studies were conducted to deal with nonsense (Technical Director). Even as ABB tried to tolerate the additional burden, client’s requests for information intensified and remained a source of irritation. ABB was forced to take drastic action. The local office was overloaded with questions and correspondence while trying to deal with concerns associated with the development and design work. The number of formal letters from the client was obvious evidence of the problems. Everyone within ABB had a feeling that little was being accomplished. The client’s J. Dahlgren, J. Söderlund / International Business Review 10 (2001) 305–322 313 behavior had become a constant source of irritation, and ABB’s operational analyses showed that the situation was becoming critical. It was then decided that ABB’s top management, including the CEO, would visit National Electric and discuss the situation with the client. Such an approach had successfully been tried in an earlier project in the United States. After the meeting, the CEO of ABB realized that he had to be more proactive. ABB had no qualified engineering competence on site, which led to extensive work for engineers located in Sweden. The situation became untenable. Our top management was spending a lot of time on this. If we’re called in to resolve issues, the system isn’t working. It’s at the wrong level. There was a risk that the project was going to be delayed and that more costs would be incurred if it continued like this. We had to come up with something (CEO). A new project manager was appointed. Management wanted to back up the project and therefore moved the initial project manager to the client’s country in order to handle questions and relations locally. We wanted to have more competence concerning the technology on site to handle all the questions from the customer and the consultants (Project Manager II). ABB’s strategy can be seen as an attempt to locally match both the client’s competence and organization. Further, the new project manager demanded that any communication from the project manager of National Electric should be channeled through him. 5.4. The problems continue The new organization did not produce any noticeable difference in Sweden. Questions continued to pour in. ABB still wanted to keep cost and time limits. The world market is small and any information of a failure spreads easily, affecting the reputation of the company. A few months later, the top management of ABB met with the client’s project manager and members of top management at a meeting in Sweden. The purpose of the meeting was to discuss and agree upon responsibility for some identified technical problems. A top management agreement was finally reached as to how responsibility should be divided. However, the meeting ended abruptly. We met in Sweden to reach an agreement. We discussed and made minor changes. Their project manager rose suddenly and declared that the National Electric representatives were leaving. They went to the airport. We sat down very confused. We managed to reach them and they then said that they wanted to talk to our CEO. This was arranged and they met at the airport. On a subsequent occasion the project manager of National Electric said that if he had been sitting closer to his own man- 314 J. Dahlgren, J. Söderlund / International Business Review 10 (2001) 305–322 ager when shared responsibility was agreed on, he would have kicked his leg (Project Manager II). The contentious atmosphere continued throughout the project. ABB’s engineers thought that the National Electric people were asking the wrong questions — questions they believed were to be sorted out later on. National Electric had their priorities, while ABB argued that other priorities would be more advantageous for the project. In the end, the plant was successfully constructed and handed over to the client, who was satisfied with its functionality. The project was not on time and budget, and according to the technical director of ABB several opportunities that could have been exploited were missed. From an ABB perspective, an enormous amount of work had been devoted to negotiations and conflict resolution, which also affected the costs for the client. 6. A theoretical interpretation Broadly speaking, we would normally regard individual behavior as influenced both by personal traits and environmental factors. The individual’s predisposition and values are of great importance for the study of any social relation, but, given our ambition to understand our case, we will here instead focus on the external influence on the outcome of behavior in social contexts. Lawrence and Lorsch (1967) recognized that different time perspectives had implications for the design of organizational structures and processes. However, this did not lead researchers to examine the implications of such considerations for the distinction between permanent and temporary settings (Bresnen, 1990). Thus there arises a great need to highlight the effects when participation is perceived as temporary, and the way appropriate organizational and management apparatus differs from permanent settings (Bryman et al. 1987, p. 256). These issues have induced us to focus on the concept of pacing in a project context. 6.1. The concept of pacing At a general level, using a term borrowed from biology, adaptation processes can be labeled ‘entrainment’, which is defined as “the adjustment of the pace or cycle of an activity to match or synchronize with that of another activity” (Ancona & Chong, 1996, p. 253). Entrainment induces scholars to look for rhythmic patterns in organizations (Gersick, 1994). Further, the concept directs researchers to analyze how well an organization’s overall pace matches the rate of change in its particular environment. Our interest in entrainment is sparked by the fact that adaptation goes on, not only between an individual and the physical environment, but also, more importantly, in social contexts. When a company, for instance, finds that a competitor has managed to get a lead in product development, it needs to speed up its own processes, in order to keep pace (Brown & Eisenhardt, 1998). Additional examples can be found in the interaction between individuals from different cultures who do not share the same per- J. Dahlgren, J. Söderlund / International Business Review 10 (2001) 305–322 315 ception of time (Levine, 1988), and in counseling where the counselor and the client need to find activity levels that match in intensity (Maple, 1985). One idea that emerges from this research is that, for any well-functioning social relation, there is a need for the establishment of a shared view of actions and time (Chapple, 1970). Strauss (1978) has labeled the necessary ‘bi-partisan common understanding’ as a ‘negotiated temporal order’. As presented above, the entrainment concept applies to individual and group levels (McGrath, 1988). We propose that the concept is equally applicable to the organizational level and to the analysis of two interacting organizations. Organizations have idiosyncratic rhythms in the form of time-schedules, accounting periods, cultures and similar ‘rhythms’, which in an inter-organizational context need to be attuned to each other for any coordination to function properly. In a social context we prefer the term pacing to the biological term entrainment. There are several reasons for this: (i) pacing refers to a context with interacting human beings and not to individuals interacting with the physical environment; (ii) pacing connotes a process with mutual adjustments and not a one-sided adaptation; and (iii) pacing does not assume any special rhythmic process for either party in the interaction although such processes might exist (e.g. the budget period). According to Gersick (1994), pacing is most likely to occur in three different cases: firstly, when the system members have a deadline, which they perceive as important; secondly, when the system members have significant control over their own actions; and thirdly, when the path to and specification of the final outcome is at least partly indeterminate. These conditions imply that system members are willing and able to alter their course in the interest of synchronization and meeting a deadline. The main purpose for using the concept of pacing is to understand how the behavior of parties in a social interaction, whether they be individuals, groups or organizations, becomes coordinated and why coordination sometimes fails. Our idea is that each member brings his or her preferences about type of activity, timing, operation, etc. to any organizational setting and that these preferences need to be synchronized for the organization to function smoothly. There are a number of different paces in a project setting. Some of these can be part of the intra-organizational interaction in the relation between a project and departments. Such pacing problems are more easily handled because of the possibility of imposing a single authority (Sayles & Chandler, 1971). The pacing concept and the conditions listed above lead us to investigate the coordination problem between client and contractor in more detail. To explain the failure of pacing, as we argue was observed in the case, we need to further elaborate on the system members’ control of their own action and their joint decision-making. We believe that the concept of matching hierarchies offers a further analytical tool for understanding projects in inter-organizational settings. 6.2. The concept of matching hierarchies One of the fundamental principles of systems theory is that for its survival an open system is dependent upon its environment to the extent that the internal structure of the system is related to the structure of the environment. In terms of Ashby’s (1956, 316 J. Dahlgren, J. Söderlund / International Business Review 10 (2001) 305–322 p. 208) well-known law: only variety can destroy variety. In dyadic project relations between organizations, the principle leads to a mapping of organizational structures. The contractor’s project organization is mirrored by a project organization of the client. This results in a configuration with matching hierarchies, as shown in Fig. 1. In our context, this logic can be seen as a way of coupling two otherwise separate systems. The figure shows that, apart from the vertical relations within each organization, the interaction process in a project setting results in a structure where lateral relations are established. At the bottom of the hierarchy, the relations involve lateral contacts between the organizations at site level. For the middle layer, the structure is made up of the project management while the top layer consists of the management of each organization. Matching hierarchies may generally be conceived of as an arrangement that has the potential of simplifying a situation by closing system boundaries in order to make it possible to handle existing problems within the limited cognitive abilities given to man (Levinthal & March, 1993). The separation of layers thus contributes to reducing, or perhaps escaping, complexity and makes action possible (Lindkvist, Söderlund, & Tell, 1998). Buffered from the rest of the organization, a certain layer of the hierarchy directs its attention to a limited part of its environment. Such an arrangement also facilitates pacing. Accordingly, the model represents an effort to make the project process more tightly coupled at each individual level. This type of configuration represents a lateral approach to the fundamental organizational principle of division of labor. By opening up the lateral relations between the organizations, each such relation economizes on management capacity, allowing top management to get involved only in the rarest of cases, and only as a last resort to solve disputes on a more informal, private ordering basis. Top management has more experience to draw from when settling conflicts, coupled with a decision capacity that provides more alternative solutions. It is important here to point to the linkage between pacing and matching hierarchies. As early as 1967, Lawrence and Lorsch argue that in a differentiated system, members will adopt different time horizons due to the environment of an organization. This would imply that each layer of a hierarchy focuses on its counterpart’s macro-cycle in order to ‘negotiate’ a temporal order. Organizing according to the logic of matching hierarchies thus not only provides a conflict resolution mechanism but also helps pacing the activities at each level. Fig. 1. Matching hierarchies. J. Dahlgren, J. Söderlund / International Business Review 10 (2001) 305–322 317 7. The case revisited 7.1. The pacing problem When the management of ABB realized that their old client was contemplating an upgrade of his plant, they contacted the client and held a seminar to inform the National Electric on the technical developments that had occurred since the previous installation. The client, however, did not seem prepared to move as quickly as might have been expected and it was not until ABB learned that National Electric was carrying out tests in plants owned by a competitor that it was clear that the client was actively working on the project. ABB, together with two competitors, were invited to tender and a normal amount of work was devoted to making calculations, designs, etc. in preparing the bid. At this stage, ABB engineers were tied up in finalizing other projects, and consequently there was no project organization in ABB. At the end of the tendering process, ABB brought in additional personnel, including a would-be project manager. After National Electric decided to give the project to ABB, additional personnel were recruited, among others the technical director. Given this sequence of events, the ABB project team was forced to start its work by studying all the documents that formed part of the basis for the contract with National Electric. ABB’s starting tempo, which did not differ from routine, was not at all compatible with the pace of the client. National Electric’s consultants had been preparing the project over a long time and had worked intensely on the details during the tender phase. They were clearly prepared to start the project right away and began asking for details and tests as part of the implementation of the contract. The reaction of ABB was to increase its effort in the project, and, when this failed, to resolve the problems by placing the project manager close to the client as a deputy project manager and appointing a new project manager at home. Despite this, ABB did not succeed in catching up with the pace of the client and they never made up for the slow start. 7.2. Violating the logic of matching hierarchies In the present case, the structural logic of matching hierarchies was violated, which caused many of the subsequent difficulties in resolving the pacing problems between ABB and National Electric. On several occasions the top management level of ABB got involved in discussions and conflict resolution with the project management level of National Electric. This occurred, for instance, at the meeting in Sweden where the CEO of ABB met members of the National Electric’s top management, a meeting in which also the project manager of National Electric took part (see Fig. 2). The project management level at National Electric was therefore on several occasions given access to the top management level of ABB. Even though this might be regarded as a way of bringing in necessary expertise or increasing the hierarchical push in the discussion, it had one very dysfunctional effect — it destroyed the conflict resolution mechanism where the management of each organization could meet without any previous involvement and commitment in the operative process of the project. In a previous project in the United States, mentioned earlier, such a contact between the management 318 J. Dahlgren, J. Söderlund / International Business Review 10 (2001) 305–322 Fig. 2. Violating the principle of matching hierarchies. level of each organization had succeeded in keeping both ABB and its American client out of the courtroom, thus avoiding a costly legal process. One possible explanation to why the principle of matching hierarchies was not honored in this case is that no truly dyadic relation existed between ABB and National Electric. The consultants, the project manager and the technical director that National Electric hired early in the process, played a far too important role. To a certain extent, it is likely that they dominated National Electric, although without totally replacing the decision capacity of the National Electric management. 8. Concluding discussion The concepts outlined in this paper were generated in order to understand and explain the problems that arose in the inter-firm relationship between ABB and National Electric. From ABB’s point of view, although including some difficult technical problems, the type of project was not unique, representing more or less normal business. For the client, however, the project had long-term effects, which made it necessary for them to acquire knowledge that could be used for managing the project after it was completed by the contractor. In a short-term relationship, the client needed to apply a long-term perspective, while, on the other hand, the contractor’s involvement was focused on the execution phase. We maintain that this situation is not uncommon. Furthermore, we argue that these characteristics are a major source of the problems of pacing observed in the case. Understanding project contexts, such as the one described, requires consideration of both structure and process dimensions. When analyzing the structure dimension, the problem seems to be to find a configuration that allows for a certain degree of coupling and joint decision-making in an otherwise fragmented organizational context. An additional requirement is that the configuration should include mechanisms for conflict resolution. In the process dimension, the problem is to find a well-functioning interplay between the parties, e.g. to solve problems with different time frames between client and contractor. The concept of pacing might be applied in order to understand the compatibility between speed and intensity of work efforts among the interacting organizations. The connotation is that in a well-functioning relationship between firms, the overall pace of each organization is synchronized, signifying a continuous and mutual adaptation process. J. Dahlgren, J. Söderlund / International Business Review 10 (2001) 305–322 319 As with process and structure, pacing and matching hierarchies are two sides of the same coin. In order to solve the problems where interdependent actors are located in different time and intensity frames, a structural configuration is called for to provide the arenas necessary for mutual adjustment. On the other hand, the structural arrangement presupposes a driving mechanism whereby the different organizational levels are connected. Connecting lateral layers is one way to establish pacing between two otherwise separate organizations. The need for pacing interdependent activities works as a driving force for establishing these links. It does seem, however, that there is a great risk that this principle will be violated, creating a triadic relationship, when the client employs consultants to whom the power to represent is transferred. This is particularly the case in technically dominated construction or development projects where the client is likely to lack the necessary competence to be able to match the contractor. The present trend of outsourcing competence provides further ground for triadic relations. The result is increased fragmentation and, in Stinchcombe’s (1985) words, a situation of ‘excessive bureaucracy’. Our case study shows that when management becomes involved in day-to-day conflicts at project management level, this precludes referring vital problems to informal conflict resolution on a management-to-management basis. Using lawyers for resolving conflicts is likely to aggravate the situation and to lead to increased tension and greater division in a situation where both parties can gain from united action. Ring and Van de Ven (1994) claim, for instance, that ‘endogenous safeguards’ are critical to interfirm relationships for two reasons. First, the greater the transaction-specific investments made under conditions of uncertainty, the more the parties involved stand to benefit from preserving the relations. Second, social–psychological processes are assumed to create a separate set of pressures to preserve the relationship. Another important reason for choosing endogenous solutions might simply be the cost involved. According to the statistics reported by Hartman (1994) as much as 20% of the cost of construction in the 1980s was attributable to the impact of litigation, and there was as much as an 11-fold increase in the number of lawyers practicing construction law between 1980 and 1990. Inter-firm projects present certain empirical characteristics, which need to be explored in-depth. We have tried to draw attention to and analyze the execution phase of such projects. The execution phase has for several reasons been neglected by previous research on projects in an inter-firm setting, either because focus has been on the selling and marketing activities of project-based firms, or because the execution phase is viewed as a relatively ‘simple’ managerial issue (Hellgren & Stjernberg, 1995). The work by Stinchcombe (1985) is here an exception. We have elaborated further on his studies and findings by providing additional explanations to the excessive bureaucracy observed in these empirical settings. As initially argued, when interdependent activities are organizationally decoupled, some mechanism for sufficient coupling must be found. In order to understand how this coupling can be accomplished, pacing and matching hierarchies can be utilized. In our conception, the pacing concept illuminates how coupling is established between organizations, how organizations agree on a temporal order and how they synchronize their respective activities. The concept of matching hierarchies, on the other hand, cen- 320 J. Dahlgren, J. Söderlund / International Business Review 10 (2001) 305–322 ters on the structure of the relationship between organizations and their hierarchical layers. Acknowledgements We are grateful for the help with the empirical work by Fredrik Tell. The comments from Hans Andersson, Professor Lars Lindkvist, Professor Ove Brandes and the anonymous reviewers considerably improved the quality of the paper. The research was funded by the Foundation for Strategic Research, IMIE, PMEX and the Jan Wallander and Tom Hedelius Foundation for Social Science Research. We acknowledge their trust and support. References Ancona, D., & Chong, C. (1996). Entrainment: pace, cycle and rhythm in organizational behavior. Research in Organizational Behavior, 18, 251–281. Ashby, E. (1956). An introduction to cybernetics. London: Chapman and Hall. Axelrod, R. (1984). The evolution of cooperation. New York: Basic Books. Bansard, D., Cova, B., & Salle, R. (1993). Project marketing: beyond competitive bidding strategies. International Business Review, 2 (2), 125–141. Bonaccorsi, A., Pammolli, F., & Tani, S. (1996). The changing boundaries of system companies. International Business Review, 5 (6), 539–560. Bresnen, M. (1990). Organising construction: project organisation and matrix management. London: Routledge. Brown, S., & Eisenhardt, K. (1998). Competing on the edge. Boston: Harvard Business School Press. Bryman, A., Bresnen, M., Beardsworth, A., Ford, J., & Keil, E. T. (1987). The concept of the temporary system: the case of the construction project. Research in the sociology of organizations, 5, 253–283. Chapple, E. D. (1970). Culture and biological man. New York: Holt, Rinehart and Winston. Chisholm, D. (1989). Coordination without hierarchy. London: University of California Press. Cova, B., & Holstius, K. (1993). How to create competitive advantage in project business. Journal of Marketing Management, 9, 105–121. Cova, B., Mazet, F., & Salle, R. (1993). Towards flexible anticipation: the challenge of project marketing. Perspectives on marketing management, 3. Cova, B., Mazet, F., & Salle, R. (1996). Milieu as pertinent unit of analysis in project marketing. International Business Review, 6 (6), 647–664. Dyer, W. G., & Wilkins, A. (1991). Better stories, not better constructs, to generate better theory: a rejoinder to Eisenhardt. Academy of Management Review, 16 (3), 613–619. Easton, G. (1998). Case research as a methodology for industrial networks: a realist apologia. In P. Naudé, & P. Turnbull, Network dynamics in international marketing. Oxford: Pergamon Press. Eccles, R. (1981). The quasi-firm in the construction industry. Journal of Economic Behavior and Organization, 2, 335–357. Eisenhardt, K. (1989). Building theories from case study research. Academy of Management Review, 14 (4), 532–550. Gersick, C. (1994). Pacing strategic change: the case of a new venture. Academy of Management Journal, 37 (3), 9–45. Goodman, R. A., & Goodman, L. P. (1976). Some management issues in temporary systems: a study of professional development and manpower — the theater case. Administrative Science Quarterly, 21 (3), 494–501. J. Dahlgren, J. Söderlund / International Business Review 10 (2001) 305–322 321 Günter, B., & Bonaccorsi, A. (1996). Project marketing and systems selling — in search of frameworks and insights. International Business Review, 5 (6), 531–537. Hadjikhani, A. (1996). Project marketing and the management of discontinuity. International Business Review, 5 (3), 319–416. Hartman, F. T. (1994). Reducing or eliminating construction claims: a new contracting process (NCP). Project Management Journal, XXV (3), 25–31. Hellgren, B., & Stjernberg, T. (1995). Design and implementation in major investments — a project network approach. Scandinavian Journal of Management, 11 (4), 377–394. Kavanagh, D. (1998). Multi-firm, temporary networks: a study of process. Unpublished PhD thesis, School of Management, Lancaster University. Keating, P. J. (1995). A framework for classifying and evaluating the theoretical contributions of case research in management accounting. Journal of Management Accounting, 7 (Fall), 66–86. Kolltveit, B. J., & Reve T. (1998). Projects — organizing, managing and implementation. Oslo: Tano Aschehoug (in Norweigian). Lemaire, J.-P. (1996). International projects’ changing patterns: sales engineers’ changing roles. International Business Review, 5 (6), 603–630. Levine, R. W. (1988). The pace of life across cultures. In J. E. McGrath, The social psychology of time. New perspectives. London: Sage Levinthal, D. A., & March, J. G. (1993). The myopia of learning. Strategic Management Journal, 14 (Special Issue Winter), 95–112. Lindkvist, L., Söderlund, J., & Tell, F. (1998). Managing product development projects: on the significance of fountains and deadlines. Organization Studies, 19 (6), 931–951. Lundin, R. A., & Midler, C. Eds. (1998). Projects as arenas for learning and renewal processes. Boston: Kluwer Academic. Macaulay, S. (1963). Non-contractual relations in business: a preliminary study. American Sociological Review, 28, 55–67. Macneil, I. R. (1980). The new social contract. New York: Yale University Press. Maple, F. M. (1985). Dynamic interviewing — an introduction to counseling. Thousand Oaks: Sage. Mattsson, L.-G. (1973). Systems selling as a strategy on industrial markets. Industrial Marketing Management, 2, 107–120. Meyerson, D., Weick, K., & Kramer R. (1996). Swift trust and temporary groups. In: R. M. Kramer, & T. R. Tyler, Trust in organizations. Thousand Oaks: Sage. Millman, T. F. (1996). Global key account management and systems selling. International Business Review, 5 (6), 631–646. Ring, P. S., & Van De Ven, A. (1994). Development processes of cooperative interorganizational relations. Academy of Management Review, 19 (1), 90–111. Sahlin-Andersson, K. (1992). The social construction of projects: a case study of organizing an extraordinary building project — the Stockholm Globe Arena. Scandinavian Housing and Planning Research, 9, 65–78. Sayles, L., & Chandler, M. K. (1971). Managing large systems. New York: Free Press. Söderlund, J., & Andersson, N. (1998). A framework for analyzing project dyads: the case of discontinuity, uncertainty and trust. In Lundin & Midler, Projects as arenas for learning and renewal processes, Boston: Kluwer Academic. Stinchcombe, A. (1985). Project management in the Nordic Sea. In A. L. Stinchcombe & C. A. Heimer, Organization theory and project management. Bergen: Norwegian University Press. Strauss, A. (1978). Negotiations: varieties, contexts, processes and social order. New York: Jossey-Bass Publications. Jörgen Dahlgren, PhD, is a Senior Lecturer of Business Administration at the School of Management, Linköping University, Sweden. He has been the dean for the School during the recent six years and is currently the leader for several on-going research projects. His research and teaching interests cover management control and project management. Jonas Söderlund, PhD, is an Assistant Professor of Business Administration in the School of Management, Linköping University, Sweden. His most recent publications have appeared in Organization Studies and Project 322 J. Dahlgren, J. Söderlund / International Business Review 10 (2001) 305–322 Management Journal. His research and teaching interests focus on project management, project marketing and temporary organizing. Söderlund is currently the coordinator of the Swedish national research initiative on project management — Project Sweden.
© Copyright 2025 Paperzz